| SDG
, according to the two seperate contracts signed with general contracter
DOŠUŽ CONSTRUCTION and TRADE A.Ž. in 1997 will realize the following tenders
for the TCK(Turkish Motorway Authority): 1 )POZANTI TARSUS AYRIMI MOTORWAY 1. SECTION LIGHTING AND ELECTRIFICATION 2 )POZANTI TARSUS AYRIMI MOTORWAY 2. SECTION LIGHTING AND ELECTRIFICATION, These jobs involve 6 different junction lightings, transformer building installation, overhead transmisssion lines, underground cable networking , sheet metal distribution transformer substations, as well as a 300 meter long tunnel ( AÇ KAPA TÜNEIŻ - Pozantż ). SDG , according to the contract signed in 1999 with ENKA & BECHTEL JV , 13 junction 110 km long ANKARA MOTORWAY LIGHTING AND ELECTRIFICATION completed the job 9 months after signing the contract. The project involved 13 different ground junction with the properties listed below:
|
|
![]() |